{{#include ../links.md}}
It is impossible to know when, or even whether, a script run will end
(a.k.a. the [Halting Problem](http://en.wikipedia.org/wiki/Halting_problem)).
When dealing with third-party untrusted scripts that may be malicious, to track evaluation progress and
to force-terminate a script prematurely (for any reason), provide a closure to the [`Engine`] via
the `Engine::on_progress` method:
```rust
let mut engine = Engine::new();
engine.on_progress(|count| { // parameter is number of operations already performed
if count % 1000 == 0 {
println!("{}", count); // print out a progress log every 1,000 operations
}
None // return 'None' to continue running the script
// return 'Some(token)' to immediately terminate the script
});
```
The closure passed to `Engine::on_progress` will be called once for every operation.
Return `Some(token)` to terminate the script immediately, with the provided value
(any [`Dynamic`]) acting as a termination token.
Termination Token
-----------------
The [`Dynamic`] value returned by the closure for `Engine::on_progress` is a _termination token_.
A script that is manually terminated returns with `Err(EvalAltResult::ErrorTerminated)`
wrapping this value.
The termination token is commonly used to provide information on the _reason_ or _source_
behind the termination decision.
If the termination token is not needed, simply return `Some(Dynamic::UNIT)` to terminate the script
run with [`()`] as the token.
Operations Count vs. Progress Percentage
---------------------------------------
Notice that the _operations count_ value passed into the closure does not indicate the _percentage_ of work
already done by the script (and thus it is not real _progress_ tracking), because it is impossible to determine
how long a script may run.
It is possible, however, to calculate this percentage based on an estimated total number of operations
for a typical run.